Carew Manor

Case Study

Client: London Borough of Sutton
Contract Administrator: MITIE
Conservation Structural Engineer: AKS WARD
Principal Contractor: Stonewest (working alongside Historic England & the Morton Partnership)
Services Provided: Conservation, Special Works

Project Overview

Restoration and dismantling and rebuilding of the structurally unstable section of the Grade II listed wall.

Key Successes

  • Assisting the Client with developing the Heritage Statement, Listed Planning Application and action all subsequent conditions.
  • Phase the works into restoration repairs and rebuilding.
  • Source suitable sympathetic materials and prepare site sample panels for Local Authority and Historic England inspection/approval.
  • Manage variations and introduce/manage specialist sub-contractors into the project.
  • Phase works to best effect.
  • Marshall pedestrian traffic and maintain safeguarding of Client’s property when wall was dismantled.
  • Monitor all works for quality control and carry out self-snagging and subsequently client inspections upon completion.

 